Wednesday, June 16, 2010

Under Ground Electricity Pit Installed

Under Ground Pit is finally done, exactly 20 business days after payment was made.

Waiting for 2nd soil test now, PD has ordered it last week, hopefully they'll do it this week.

2 comments:

  1. Hi Guys,

    discovered you are following my blog.

    building is never easy and I wish you the best.

    quick comment on your electrical pit - noticed they have put asphalt. I would go back to Jemena ASAP to get them to concrete it because you may run into trouble with council. They did the exact same thing at my house, the council chucked a fuss and after much wrangling they are going to pay for it. Alternatively you could wait until all the construction is done then get them to fix it.

    Also with your asset protection permit - if you haven't alread done so - get council in to inspect and get your deposit back. Let PD apply for an asset protection permit and let them be reponsible for any damage to footpaths etc because it will happen. It may set your building time back a few days but it will save you a lot of grief at the end.

    Cheers,

    Sean

    ReplyDelete
  2. Thanks for the tips, exactly the things I need. That's the reason I'm following those people who did demo job, to get ideas & make sure I don't miss anything.