Built Camberwell 29 with Porter Davis. Site Start was 27 July 2010 and Handover was 22 December 2010.
Tuesday, August 17, 2010
Day 21: Nothing
Nothing's been done for the last 2 weeks. We still haven't got the piers & slab done yet. Guess the weather been too wet for them to be able to do it. Hopefully we'll get a bit more of sunshine the next few days so that they can start work again.
Thursday, August 5, 2010
Day 7: Pipes, Drainage, Meter Box & Retaining Wall
Thursday, July 29, 2010
Tuesday, July 27, 2010
Day 1: Site Start
Thursday, July 22, 2010
Slab Drawing & site start
Drawing for the Slab. We'll have 42 piers under the slabs. The 2nd soil test confirmed that our soil is one of the worst there is.

Got a call from Luke, the building supervisor. Site start will be Mon 26/07/10, weather permitting. Concrete is scheduled to be poured on Mon 09/08/10, weather permitting.

Got a call from Luke, the building supervisor. Site start will be Mon 26/07/10, weather permitting. Concrete is scheduled to be poured on Mon 09/08/10, weather permitting.
Sunday, July 11, 2010
A Start Soon?
Porter Davis has updated status on the 24/7 Portal. Council permit received & Administration Completed. Hope they will commence building very soon.
Saturday, July 3, 2010
Asphalt & second soil test
The asphalt used to cover the footpath after Jemena did the Under Ground Pit sunk (see photo below). Trying to get them to replace the asphalt with reinforced concrete.

PD has received the result of 2nd soil test & the engineering department is working on it. They are also applying for the permit soon, so hopefully we'll have a site start within the next week or two.

PD has received the result of 2nd soil test & the engineering department is working on it. They are also applying for the permit soon, so hopefully we'll have a site start within the next week or two.