Built Camberwell 29 with Porter Davis. Site Start was 27 July 2010 and Handover was 22 December 2010.
Thursday, July 22, 2010
Slab Drawing & site start
Drawing for the Slab. We'll have 42 piers under the slabs. The 2nd soil test confirmed that our soil is one of the worst there is.
Got a call from Luke, the building supervisor. Site start will be Mon 26/07/10, weather permitting. Concrete is scheduled to be poured on Mon 09/08/10, weather permitting.