Floating Floor Board is yet to be done. SS told me it would be done by Monday this week, but it is still not done yet.
They have fixed the down pipes. They replaced the one above the meter box so that the spout aligned correctly to the down pipe.
They are still to do the electrical for the theatre room & living room.
Not long to go now, only 2 weeks to go before the 140 building days is up. We've received the final invoice & was told that the SS & CSC will contact us re PCI. Will get the building inspector to go through the house as soon as the floating floor board is installed.
Fencing will be done in early January & Driveway will be done in mid January. Can't do it before Christmas, everyone is busy in December.