Day 118: Inspection & Cross Over

Had an on site appointment with the SS who didn't turn up until I called him & the office numerous times. He thought the inspection is tomorrow. He turned up more than an hour late.

Most things have been done except the feature walls, garage door, home theatre cabling and floating floor board. The supplier ran out of stock of the floor board that we chose, so they gave us an alternative & we took it rather than delaying the completion of the house.

View of the house from the street


David from Whitehorse City Council came to check the cross over. We requested a slightly wider than standard cross over & he was fine with it. Now all we need to do is find a concreter to do our driveway & cross over.