100 days have gone since start of the construction, 40 days to go.
Had a site meeting with the SS this afternoon, he said they'll most likely finish the construction work by end of the month & we can expect hand over early December.
Went through the house with him, few things to be done:
- Leaking front pipe still not fixed yet.
- Home Theatre cabling are not done, he'll have to get the final drawing to fix this.
- Door handles for laundry doors are omitted from drawing.
- A couple of outdoor wiring not done.
- Electrical for ceiling fan for Alfresco is not done.
Tiling has also been completed, so it seems we are on track to have Christmas in the new house.
Will have to organise quotation for Fencing & Blinds/Curtains so that they can be done just after the hand over.