Had our Pre Hand Over Inspection at noon today & everything went well. No major problems & nothing that can't be fixed within few days. Will get the report tonight.
Then later on in the afternoon, we had our PCI. Lotsa paint touch up to be made, I won't even bother with 75% of it but the SS put the dots everywhere & wanted to make sure they are fixed. Other things to be rectified are:
Chip to Pot Drawer
Rangehood not level
Window glazing is short to the dining room window
Bathroom window rubber is coming off
Toilet is not working properly - can't refill the empty tank.
Overall I think the quality is pretty good.
Hand over is scheduled for Thursday next week. Hopefully the bank will be able to issue the cheque in time.