100 days have gone since start of the construction, 40 days to go.
Had a site meeting with the SS this afternoon, he said they'll most likely finish the construction work by end of the month & we can expect hand over early December.
Went through the house with him, few things to be done:
- Leaking front pipe still not fixed yet.
- Home Theatre cabling are not done, he'll have to get the final drawing to fix this.
- Door handles for laundry doors are omitted from drawing.
- A couple of outdoor wiring not done.
- Electrical for ceiling fan for Alfresco is not done.
Tiling has also been completed, so it seems we are on track to have Christmas in the new house.
Will have to organise quotation for Fencing & Blinds/Curtains so that they can be done just after the hand over.
Built Camberwell 29 with Porter Davis. Site Start was 27 July 2010 and Handover was 22 December 2010.
Thursday, November 4, 2010
Tuesday, November 2, 2010
Day 98: The Race that stops a Nation
Melbourne Cup day is dubbed as the race that stops a nation. However it didn't stop the tiler to continue working. Not much else happening, still waiting for the plumber to fix the front water tap leak & still waiting for the SS to get the tradie to install the still flashing for our front door.
Monday, November 1, 2010
Day 97: Tiling work continues
Saturday, October 30, 2010
Day 95: Painting Continued, Tiles Delivered & Pipe Leaked again.
Painting continued during the week, they started painting the gutter yesterday & the eves were given 2nd coat of paint.

Bifold door has been stained as well, looking good.

Tiles were delivered on Thursday.

They started to waterproof the ensuite & bathroom, I wonder why they didn't do the whole ensuite/bathroom at the same time.

Interior painting has been completed

Supposed to have an onsite meeting with the SS to go through the lockup & fixing stage completion. He cancelled the meeting & rescheduled for next week. I'm still refusing to pay the fixing stage until the Sill Flashing on the Front Door is installed. The SS insisted that it's been done, he must have thought that I'm blind not to be able to see whether it's been done or not.
Our front tap water leaked again on Thursday, texted & emailed the SS to let him know about it & he said they would send the plumber first thing Friday morning. Went to check on Friday evening & nothing was done. The neighbours are not happy with the water wasted & how PD been handling this, the 2nd time in 2 weeks.

Bifold door has been stained as well, looking good.

Tiles were delivered on Thursday.

They started to waterproof the ensuite & bathroom, I wonder why they didn't do the whole ensuite/bathroom at the same time.

Interior painting has been completed

Supposed to have an onsite meeting with the SS to go through the lockup & fixing stage completion. He cancelled the meeting & rescheduled for next week. I'm still refusing to pay the fixing stage until the Sill Flashing on the Front Door is installed. The SS insisted that it's been done, he must have thought that I'm blind not to be able to see whether it's been done or not.
Our front tap water leaked again on Thursday, texted & emailed the SS to let him know about it & he said they would send the plumber first thing Friday morning. Went to check on Friday evening & nothing was done. The neighbours are not happy with the water wasted & how PD been handling this, the 2nd time in 2 weeks.
Friday, October 22, 2010
Day 87: Painting Started
Wednesday, October 20, 2010
Tuesday, October 19, 2010
Day 84: Fixing Stage Completed
Got an invoice for Fixing Stage. Things are going on very quickly, they are working inside now & the doors been locked most days, however they didn't lock it today.
Roof Capping was finally fixed.
However, the damage is already done, the heavy rain over the weekend has damaged the ceiling plaster in the ensuite. Water Damage as marked by the plasterer
It seems they are going to replace this panel of plaster.
View of the kitchen from living area
Laundry cabinets done
View of the living room & rumpus from the kitchen
Ensuite cabinets done
Bathroom cabinets done
Roof Capping was finally fixed.
However, the damage is already done, the heavy rain over the weekend has damaged the ceiling plaster in the ensuite. Water Damage as marked by the plasterer
It seems they are going to replace this panel of plaster.
View of the kitchen from living area
Laundry cabinets done
View of the living room & rumpus from the kitchen
Ensuite cabinets done
Bathroom cabinets done