Wednesday, August 25, 2010

Day 29: Slab Preparation

They started the slab preparation yesterday afternoon in the rain & continued today. Seems that they are planning to pour the concrete very soon.

Monday, August 23, 2010

Day 27: Piers Done

All the piers were done, so hopefully we'll have the slab done soon, weather permitting.


Tuesday, August 17, 2010

Day 21: Nothing

Nothing's been done for the last 2 weeks. We still haven't got the piers & slab done yet. Guess the weather been too wet for them to be able to do it. Hopefully we'll get a bit more of sunshine the next few days so that they can start work again.

Thursday, August 5, 2010

Day 7: Pipes, Drainage, Meter Box & Retaining Wall

Work is continuing, they've now installed the Meter Box, Retaining Wall, Drainage & Pipes.

Luke the SS called me & told me that they are going to do the piering this week & Slab to be poured either on Monday/Tuesday, weather permitting. Followed by meeting on site after the slab has been poured.



Thursday, July 29, 2010

Day 3: Temp Fence, Temp Toilet & Cage for Rubbish

Temporary fence is up today. Temporary toilet & cage for rubbish are also delivered.

Tuesday, July 27, 2010

Day 1: Site Start

Finally we have commencement of building work. Work to be completed within 160 days of today, fingers crossed it will be before Christmas.

Thursday, July 22, 2010

Slab Drawing & site start

Drawing for the Slab. We'll have 42 piers under the slabs. The 2nd soil test confirmed that our soil is one of the worst there is.


Got a call from Luke, the building supervisor. Site start will be Mon 26/07/10, weather permitting. Concrete is scheduled to be poured on Mon 09/08/10, weather permitting.